The article belongs to the category:Legal Update

Energy and Infrastructure Client Update – a review of PUA’s hearings

October 2015

Attached please find a review of PUA’s hearings dated October 14, 2015, concerning its resolutions to allocate 45 MW for small PV power plants (of up to 5 MW each) and 70 MW for large PV power plants (of more than 5 MW each).

As detailed in the review, both resolutions determine ranked Tariffs, starting with NIS 0.27 per KW and up to NIS 0.311 per KW.

Responses to the proposed resolutions may be submitted by November 10, 2015.

Click here for client update (Hebrew).